3-5 Duke Street, W1 - 1st Floor Office
Project Overview
Client
The Portman Estate
Start Date
24.04.2023
Finish Date
12.06.2023
Value
£195,000.00
Form of Contract
JCT with Contractors Design Portion

Project Description
Refurbishment of existing 1st floor office suite.
Works involved:
-
Full strip out to form open plan office
-
Dry-lining works
-
M&E installation
-
New Kitchen / tea point
-
Floor finishes
-
New Sanitaryware
-
Secondary Glazing
Challenges Overcome
-
Working within an occupied building, ensuring segregation of the works and residents at all times.
-
Noise concerns for residents, accommodating working from home- on / off working to accommodate but still maintaining programme on site.
-
Old services- having to upgrade water services and Electrical supply- running new supplies within an occupied building.
-
Deliveries within an extremely tight road- logistics and traffic management plan well maintained.