11 Weymouth Street
Project Overview
Client
The Howard de Walden Estate
Start Date
01.08.2023
Finish Date
01.09.2024
Value
£2,100,000.00
Form of Contract
JCT Intermediate Building Contract with CDP

Project Description
-
Full Building Refurbishment, Internal & External
-
Cut & Carve Structural Adaptions
-
New M&E Installation Including Utilities
-
Underground Drainage Installation with Acoustic Stud Detailing
-
Tanking to Basement Areas
-
New Staircases
-
Fit Out 4Nr New Residential Flats, converted from office spaces, across 6 Floors
-
Sustainability Targets for Heat Pumps, Air Tightness

Challenges Overcome
-
Structural Steelwork Install required around main building entrance, ensure site access remained safe for material loading into site.
-
Sequencing mains service installs with acoustic stud rail system (required due to building above underground railway line)
-
Achieving ait tightness score below 7 with large air handing units & air conditioning installed on each floor.
-
Building Control went into administration so full project review, alter & response required once Westminster building control were appointed.