Peace Childrens Centre - Audiology
Project Overview
Client
Silk Partnership Building Surveyors for Hertfordshire Community NHS Trust
​
Start Date
03.02.2025
Finish Date
25.04.2025
​
Value
£288,000.00
​
Form of Contract
JCT

Project Description
GD Construction were tasked with stripping out an array of existing office spaces and the existing audiology suite. To re-construct the area to form a new layout and to complete a full refurbishment of the space. Services provided by GD Construction:
​
-
New 600x600 grid ceilings
-
New lighting
-
New power and data
-
New electrical distribution
-
New vinyl floorings
-
New decorations
-
New fire rated doorsets and ironmongry
-
New partitions
-
New air conditioning
-
New ventilation
-
New IPS units
-
Fire stopping
-
Specialist services re-installation
-
FFE






Challenges Overcome
-
Working within a live NHS centre with council patients and staff operating the wider area.
-
Due to the above, noise restraints were considered.
-
Deliveries and logistics were compromised due to the routes through the Live demise.