 Howard Court – Reconfiguration of Unit 1B

Project Overview

 

Client

Hertfordshire Community NHS Trust 

Start Date

23.06.2025

Finish Date

08.08.2025

Value

£101,575.30

Form of Contract

Tendered Project

IMG_6204.JPG

Project Description

 

Internal Reconfiguration Works to vacant 1st Floor Office area to afford new roller racking storage facilities, new metal studwork partitions, new electrical services, floor coverings, complete redecoration.

Challenges Overcome

 

All noisy operations (initial demolition strip-out, drill fixings to structural ceiling, alterations to existing mechanical and electrical services actioned out-of-hours, early mornings and weekends.

GD-Logo-Red.png

Contact

 

Unit 4 Spring Valley Business Centre, Porters Wood, St Albans, Hertfordshire. AL3 6PD

T: 01727 811 442

E: info@gd-construction.co.uk

 

 

GD Construction (St Albans) Ltd © 2021. All rights reserved. Web design by daveidesign limited.

Like us, love us, share us

Social Media Icons white.png
Social Media Icons white.png
Social Media Icons white.png
bottom of page