Clockhouse Primary School
Project Overview
Client
Clockhouse Primary School
Start Date
30.06.2023
Finish Date
18.08.2023
Value
£250,000.00
Form of Contract
HBW Partnership

Project Description
The works comprised of the refurbishment of classroom blocks, toilets and staff rooms and external works all carried out during the school holiday period. The works involved new windows, new floors, ceilings and wall finishes with full redecorations and alterations to canteens and toilets. New play areas were constructed with new perimeter fencing.
-
New windows.
-
New lighting.
-
New heating system.
-
New flooring.
-
New Doors and Fixings.
-
Complete Redecoration.
-
Fencing & external works.
Challenges Overcome
The school is used during the summer holidays so careful site segregation was employed and stringently adhered to. All site deliveries were met at the gates and escorted to the site compound.