1a Duke Street, W1
Project Overview
Client
The Portman Estate
Start Date
14.08.2023
Finish Date
20.10.2023
Value
£150,000.00
Form of Contract
JCT with Contractors Design Portion

Project Description
Refurbishment of existing ground floor office suite and conversion of the external courtyard to form new lower ground floor WC area.
Works involved:
-
Full strip out
-
Dry-lining works
-
M&E installation
-
New kitchen / tea point
-
Floor finishes
-
New Sanitaryware
-
Secondary glazing
Challenges Overcome
-
Working within an occupied building, ensuring segregation of the works and residents at all times
-
Noise concerns for residents, accommodating working from home –on/off working to accommodate but still maintaining programme on site
-
Old services- having to upgrade water services and Electrical supply- running new supplies within an occupied building
-
Deliveries within an extremely tight road- logistics and traffic management plan well maintained.